How adherence to public procurement is inflicting high costs and creating a disaster for the country
When David Jamwa was appointed Managing Director of the National
Social Security Fund (NSSF), he found the Fund in the final stages of
procuring a contractor to build a 29-floor Pension Towers on Lumumba
Avenue. Roko Construction won the tender of Shs $21m. The structure did
not optimally utilize the land and its value as its rate of return was
estimated at 18%. Jamwa asked the architects to design a new structure
to maximize returns from the plot.
The NSSF architect did a new design of 52 floors. It was given to a
quantity surveyor who returned a sum of $55m as its likely cost, which
would have increased the rate of return to 18%. Meanwhile, Roko were
already on the site excavating the ground. Jamwa asked them to excavate
according to the new design to create six underground parking floors
instead of two as previously planned. They were willing to build the new
design at the sum given by the NSSF quantity surveyor. Jamwa wrote to
PPDA to give a waiver so that instead of re-tendering (which would last
another two years), NSSF keeps Roko by single sourcing.
It was clear that Jamwa had violated many procurement rules. He had
changed the design of a building whose tender had been awarded. He had
instructed Roko to excavate for the new design without retendering. But
his decision was right from both a business point of view and from the
view of rationality. I was in the office of Chris Kasami (then Finance
Permanent Secretary/Secretary to Treasury) with his deputy, Keith
Muhakanizi, when a debate on this issue came up. Muhakanizi argued that
regardless of Jamwa’s violations, retendering would be costly. You
either had to hire Roko to build the new design or compensate them for
the contract they had won and which was going to be cancelled.
But in complete disregard of rationality (by adhering strictly to
procedures and the law), the IGG ordered that the entire process be
stopped as she investigated. When her report came out a year later, she
found all these procedural violations by Jamwa and ordered a
retendering. Meanwhile, Roko had stopped their work and their equipment
was lying idle. Under the contract, this allowed them to claim
compensation for time lost that was due to delays caused by NSSF. Roko
had workers and equipment on site all of which were costing it money.
Worse still, in 2008, the dollar was worth Shs 1,600, a bag of cement
Shs 13,000 and a litre of Petrol Shs 1,800. NSSF went without a board
or substantive MD for almost two years. When Richard Byarugaba was
appointed in 2010, the dollar had risen to Shs 2,300, a bag of cement to
Shs 28,000 and a litre of petrol to Shs 3,700. He immediately initiated
a retendering process, which lasted two years. When it was finally
awarded in late 2012, Roko lost to a Chinese company, CCECC; and the new
contract sum was $95m.
Meanwhile after excavating the ground to prepare for six underground
floors, a risk developed. Nakasero Road and Lumumba Avenue were about to
collapse, endangering the lives of motorists. NSSF asked PPDA for a
waiver to get Roko to build the six underground floors to hold both
roads. Under such emergency conditions, Roko bargained hard.
Compensation for delays and these works came to $16m making the entire
project cost $110m – double the initial sum. That is the cost of trying
to correct Jamwa’s procedural mistake. Is that desirable?
This situation has played out in the tender for the National ID
Project (where work delayed for seven years and project costs tripled)
and Bujagali Power Dam (where works delayed for ten years and the
project sum doubled). And it is happening now for Mukono-Katosi Road.
The company that won the tender to build the 74km road, Eutaw
Construction Company Inc of Florida, is a briefcase company with no
capacity to do the work. But it did what UNRA failed to do – it has
subcontracted a competent Chinese company, CCECC, which built the Fort
Portal-Bundibugyo road. CCECC is on the ground with equipment and doing
the work.
However, according to the contract, Eutaw is only allowed to
subcontract only 30% of the works. The challenge for Uganda is whether
to actually allow UNRA do a direct procurement of CCECC and therefore
finish the road within the budget and on time or to cancel it and order a
retendering. However, retendering – in the best-case scenario and
assuming no one complains about the procedures – lasts 18 months. With
prices of things like cement, dollars, bitumen, fuel etc. going up, it
is possible that the contract sum can go up. That means that the road
may delay for another four years and be done at double the cost.
This is where my disagreement with the IGG begins. In her defense
against my criticism, she correctly cites the Constitution, the act
establishing her office and its mandate and the procurement laws of
Uganda. All that is fine. However, the law is not a substitute for
common sense. If a strict, adherence to the law delays major government
projects and multiplies the costs by a factor of two or three, then
common sense must set in. As Jesus advised overzealous Pharisees
implementing Jewish law, the Sabbath was made for man; man was not made
for the Sabbath. Equally, the law is made for Ugandan citizens; Ugandans
are not made for the law.
Decisions about violation of procedures should never miss sight of
the goal that is sought – getting a good quality service at the best
price available in the shortest time possible. Adhering to every rule
can be costly as the NSSF’s Pension Towers on Lumumba Avenue example
demonstrates. In such cases, it is important to exercise rational
judgment and bend some rules where necessary. I am not saying we remove
procedures entirely. They are very, very important. But where they
undermine realization of the main objective, pragmatism must be
employed.
Many countries, beginning with Singapore, have since discovered that
procurement and other government rules and procedures can be cumbersome
and counterproductive. Nations like Australia, Canada and New Zealand
reformed their procurement systems. Rather than emphasize adherence to
procedures, they hold public officials accountable for results. Did you
deliver the right service at the right price, within the right time
frame at the required standard? Thus where strict adherence to
procedures undermines the main aim, a public official is allowed to
sidestep them.
amwenda@independent.co.ug
Monday, September 8, 2014
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment